 Schedule:

  • Week 1: (June 5) Plan Layout and Schedule
  • Week 2 (June 12): Framing/Windows and Doors
  • Week 3 (June 19): Demolition
  • Week 4 (June 26): Rough Plumbing and Electrical
  • Week 5 (July 3): Insulation
  • Week 6 (July 10): Sheetrock & T, B & T
  • Week 7 (July 17): Cabinets
  • Week 8 (July 31): Countertops
  • Week 9 (Aug. 7): Trim and Flooring
  • Week 10 (August 14): Paint
  • Week 11 (August 21): Plumbing Fixtures and Electrical Trim
  • Week 12 (August 28): Appliances & Overview
The plans above show the final layout of the kitchen. We will be gutting the existing kitchen, framing up a new 340 square foot addition and then finishing out both rooms as described in the plans to the left.

"Kitchen to Die For" was produced by Chris Miles and HouseTalk. If you have questions on this project please click here to e-mail Chris: chris@remodelingshow.net


Site Design & Hosting by PCA Web Design & Hosting
For more information contact us at: info@pcawebdesign.com

© Copyright 2001-2003